West Rail Systems Testing

The West Rail Line is officially in the integrated testing phase! The first sequence of testing will be to ensure all at-grade crossings operate correctly when a train is approaching.  This will begin on January 3, starting at Zuni Street in Denver, continuing west, and ending January 19, 2013 at Johnson Road in Golden.  Testing at each crossing takes 1-2 days and multiple crossings will be tested per day.  Below is a tentative schedule of when each crossing will be tested.  There will be intermittent delays and flaggers will be on-site to assist with traffic control.

 

We appreciate your cooperation during these activities and apologize for any inconvenience this may cause.

 

*Scheduled dates are subject to change.

 

 

Crossing Duration (days) Start Finish
Zuni

1

1/3/2013

1/3/2013

Decatur

1

1/3/2012

1/3/2013

Knox

1

1/4/2013

1/4/2013

Perry

1

1/4/2013

1/4/2013

Harlan

2

1/5/2013

1/6/2013

Lamar

2

1/5/2013

1/6/2013

Pierce

2

1/5/2013

1/6/2013

Teller

2

1/5/2013

1/6/2013

Carr

2

1/5/2013

1/6/2013

Estes

1

1/7/2013

1/7/2013

Garrison

1

1/7/2013

1/7/2013

Independence

1

1/7/2013

1/7/2013

Oak

2

1/8/2013

1/9/2013

Quail

2

1/8/2013

1/9/2013

Collins

2

1/8/2013

1/9/2013

8th

2

1/8/2013

1/9/2013

North E.

2

1/8/2013

1/9/2013

North W.

2

1/10/2013

1/11/2013

Ulysses

2

1/19/2013

1/20/2013

Earl Johnson

2

1/19/2013

1/20/2013

 